Monday, January 23, 2012

Brasada Ranch (Lot 182) 01/20/2012

Interior paint is complete; interior doors installed; millwork begins; tile prep begins.













Pronghorn (Lot 62) 01/20/2012


Roof tiles have arrived; windows have been installed; rough plumbing and rough electrical continue.







Tuesday, January 3, 2012

Brasada Ranch (Lot 182) 12/30/2011

Siding and stone continues. Drywall texture is complete and ready for paint.